In less than a week we have raised 105 defects. A great testing effort and thanks to all that have helped!
Right now we have 4 awaiting re-test and only 16 still in progress with dev team.
Our biggest problem is Microsoft!
Yes, no surprise, IE8 is causing us the most trouble. The dev team is getting there, but it makes you wonder what on earth Microsoft do with their applications to make them so hard to work with - especially their countless attempts at IE.
A lot of work still to do and approx 8 hours before we make "Go, No Go" decision.
Tuesday, June 30, 2009
Thursday, June 25, 2009
We're in UAT
The software was dropped into Staging at a bit before 5pm yesterday.
We are having some issues with IE6 and IE8. At this stage it looks like a lot of the problems are browser related.
Some tidy up required to make the package easier to use and a bit more intuitive.
Overall pretty happy with where we are. 38 defects raised so far.
We are having some issues with IE6 and IE8. At this stage it looks like a lot of the problems are browser related.
Some tidy up required to make the package easier to use and a bit more intuitive.
Overall pretty happy with where we are. 38 defects raised so far.
Wednesday, June 24, 2009
Final countdown!
We are now on the final countdown to staging and UAT.
R1 should be delivered to Testing this afternoon and we currently have 8 tester lined up for UAT!
Very excited to see what R1 looks like - I've only seen conceptual designs and story boards so far.
R1 should be delivered to Testing this afternoon and we currently have 8 tester lined up for UAT!
Very excited to see what R1 looks like - I've only seen conceptual designs and story boards so far.
Friday, June 19, 2009
End of a good week
The week has gone from average to really good.
Development agreement now agreed
All static info delivered
Design concepts 98% there
Code almost complete
5 Testers lined up for next week
Stationery designed and at print
Promo items at print
Launch competition prize confirmed
All on track!
In fact it's all going so well, I'm off to Byron for the weekend!
Need a few more tester, but I'll worry about that on Tuesday.
All on track!
In fact it's all going so well, I'm off to Byron for the weekend!
Need a few more tester, but I'll worry about that on Tuesday.
Thursday, June 18, 2009
Todays plans...
Today we need to finalise all the T&Cs and legal copy. Fun, fun, fun!
All legal copy must be ready to drop by tomorrow.
All legal copy must be ready to drop by tomorrow.
Wednesday, June 17, 2009
Design 95% there
The design for Release 1 is about 95% there. some final tweaks and we're ready for UAT next week.
Once we sign off on the design the code will be dropped into the template and hopefully it will all fit...
Great news at the end of a hard day!
Once we sign off on the design the code will be dropped into the template and hopefully it will all fit...
Great news at the end of a hard day!